Critical Path Method (CPM)

James E. Kelley Jr. and Morgan R. Walker · 1959

Finds the longest chain of dependent activities, which sets the shortest possible project duration.

Diagram of Critical Path Method (CPM). Its parts are listed below. Opens full size in a new tab.

Helps with

  • which tasks could delay the whole project
  • scheduling a project with many dependent tasks
  • working out the shortest project duration
  • which tasks have slack and which do not

Use it when

Scheduling a project with many dependent tasks.

The parts

  • List the activities
  • Estimate durations
  • Map dependencies
  • Find the longest path
  • Calculate float
  • Manage the critical path

Watch out

It assumes fixed durations and unlimited resources, so the critical path shifts once people are shared or estimates slip.

Where it comes from

The related PERT technique was published the same year by Malcolm, Roseboom, Clark and Fazar in Operations Research.

Source: Kelley, J. E. and Walker, M. R. "Critical-path planning and scheduling". Papers presented at the Eastern Joint IRE-AIEE-ACM Computer Conference, Boston, 1-3 December 1959, pp. 160-173 (opens in a new tab)