Earned Value Management (EVM)
Compares the value of work done with its planned and actual cost to measure schedule and cost performance.
Helps with
- is the project on budget and on schedule
- tracking cost and schedule performance
- spotting early that a project is overspending
- measuring progress against the plan in money terms
Use it when
Tracking whether a large project is on budget and on schedule.
The parts
- Planned value (PV)
- Earned value (EV)
- Actual cost (AC)
- Schedule variance (EV - PV)
- Cost variance (EV - AC)
- SPI = EV / PV
- CPI = EV / AC
Watch out
Earned value only means something if the baseline and percentage-complete measures are honest; it tracks cost and schedule, not quality.
Where it comes from
DoD issued it in 1967 as cost/schedule control systems criteria (C/SCSC) under DoD Instruction 7000.2; the earned value management name came later.