Weighted Shortest Job First (WSJF)

Don Reinertsen; popularised by SAFe · 2009

Orders work by its cost of delay divided by its size, so small urgent valuable jobs go first.

Diagram of Weighted Shortest Job First (WSJF). Its parts are listed below. Opens full size in a new tab.

Helps with

  • how to prioritise a backlog by cost of delay
  • which jobs to do first when delay is costly
  • sequencing work by value and size
  • small urgent jobs stuck behind big ones

Use it when

Sequencing a backlog where delay has a real cost.

The parts

  • User-business value
  • Time criticality
  • Risk reduction / opportunity enablement
  • Job size

Watch out

Relative scores are easy to game, and the formula only helps if cost of delay is estimated honestly.

Where it comes from

Reinertsen divides cost of delay by job duration in money and time, applying the weighted-shortest-processing-time rule from scheduling theory (Smith, 1956); SAFe estimates cost of delay as the sum of the first three parts on a relative scale and uses job size for duration.

Source: Reinertsen, D. G. The Principles of Product Development Flow: Second Generation Lean Product Development. Redondo Beach, CA: Celeritas, 2009 (opens in a new tab)

SAFe is a trademark of Scaled Agile, Inc.